Rectangular section
Used for slabs, walls, rectangular columns, trenches and pad footings.
Volume = Length × Width × DepthCalculator
Calculate concrete volume, dry mix allowance, ready-mix quantity, bags, and estimated cost.
The calculator applies the formula shown in the result cards and updates instantly as values change.
Editable rates, odds, values, and percentages should match your current source, supplier, or platform data.
Calculations run in your browser. No extra API request is needed for these estimates.
A concrete calculator converts project measurements into a practical estimate for slabs, foundations, footings, walls, columns, post holes, steps and other concrete elements. Enter the relevant dimensions to find the net concrete volume, adjusted purchase quantity, approximate number of bags and estimated material cost.
The volume formula is usually simple. Accurate measurement is the more important part. Excavations can vary in depth, formwork may not be perfectly straight, and some material may remain in a mixer, chute or pump line. A useful estimate therefore shows both the exact geometric volume and a separate allowance for normal site variation.
Follow these steps before buying concrete bags or requesting a ready-mix quotation.
A project has a net volume of 10 cubic metres. Applying a 7.5% allowance gives:
10 × 1.075 = 10.75 m³When a supplier accepts orders only in 0.5 m³ increments, the practical order may be rounded to 11 m³. Confirm minimum-load rules and accepted ordering increments directly with the supplier.
The Percentage Calculator can be used to check percentage additions or compare two project estimates.
Concrete is measured by volume because it fills a three-dimensional space. The correct formula depends on the shape of the element being poured.
Used for slabs, walls, rectangular columns, trenches and pad footings.
Volume = Length × Width × DepthUsed for circular slabs, post holes, round columns and cylindrical bases.
Volume = π × Radius² × DepthThe inner cylindrical volume is deducted from the outside volume.
Volume = π × (Outer radius² − Inner radius²) × HeightLength, width and depth must be expressed in compatible units before multiplication. When length and width are entered in metres, a thickness shown in millimetres must first be divided by 1,000.
A 150 mm slab thickness is therefore entered as 0.15 m when calculating manually:
150 ÷ 1,000 = 0.15 mFor imperial measurements, divide inches by 12 before multiplying values measured in feet.
4 inches ÷ 12 = approximately 0.333 footSlabs include building floors, driveways, patios, warehouse floors, equipment bases, concrete yards and walkways.
Measure the internal length and width of the formed area together with the actual slab thickness. Calculate beams, thickened edges and machinery bases separately.
Slab volume = Length × Width × ThicknessMeasure the total trench length, average width and average depth. Split the trench into separate sections where its size changes.
Strip footing volume = Total length × Width × DepthCalculate one footing and multiply the result by the number of identical units. Create a new group for every different footing size.
Total volume = Length × Width × Depth × QuantityMeasure wall length, height and thickness. Large door, window or service openings may be deducted from the gross wall volume.
Wall volume = Length × Height × ThicknessMultiply the column width by its depth and height, then multiply by the number of identical columns.
Column volume = Width × Depth × Height × QuantityEnter the column diameter and height. The radius used in the formula is half of the measured diameter.
Column volume = π × Radius² × Height × QuantityCalculate one hole as a cylinder and multiply it by the number of holes. The embedded volume of a large post can be deducted when it materially changes the result.
Post-hole volume = π × Radius² × Depth × QuantityThis method can be used for tank bases, round equipment pads, circular foundations and other cylindrical pours.
Circular slab volume = π × Radius² × ThicknessStairs may contain individual steps, a supporting waist slab, landings and beams. Divide simple solid stairs into measurable sections. Structural stairs should be measured from approved drawings.
Calculate the cross-sectional area of the kerb or channel and multiply it by the full installed length.
Volume = Cross-sectional area × Total lengthCalculate the normal slab first. Measure the extra depth and width of each thickened edge separately, then add that additional volume to the slab total.
Local foundations below plant or machinery often have greater depth than the surrounding floor. Treat every base as a separate concrete section.
Mixing measurement systems is a common cause of incorrect results. A slab may be measured in metres while its thickness is shown in millimetres, or measured in feet while its depth is shown in inches.
| Measurement | Equivalent | Typical use |
|---|---|---|
| 1 metre | 1,000 millimetres | Lengths, widths and heights |
| 100 millimetres | 0.10 metre | Thin slabs and paths |
| 125 millimetres | 0.125 metre | Slab thickness conversion |
| 150 millimetres | 0.15 metre | Slab thickness conversion |
| 200 millimetres | 0.20 metre | Deeper structural sections |
| 1 cubic metre | 1,000 litres | Ready-mix volume |
| Measurement | Equivalent | Typical use |
|---|---|---|
| 1 foot | 12 inches | Lengths, widths and depths |
| 4 inches | Approximately 0.333 foot | Slab thickness conversion |
| 6 inches | 0.5 foot | Slab thickness conversion |
| 1 cubic yard | 27 cubic feet | Ready-mix ordering |
| 1 cubic metre | Approximately 1.308 cubic yards | Metric-to-imperial conversion |
A geometric calculation assumes that the finished excavation and formwork are exact. Actual construction conditions may require a slightly larger quantity. There is no single percentage that is suitable for every project.
| Site condition | Example allowance | Points to consider |
|---|---|---|
| Accurately formed work | Approximately 5% | Formwork, dimensions and levels have been carefully checked. |
| Typical site conditions | Approximately 7.5% to 10% | Allows for ordinary measurement variation and minor placement loss. |
| Irregular excavation | 10% or more | Depth, width or ground level varies across the pour. |
| Complex shapes or uncertain dimensions | Project-specific review | Divide the work into smaller sections and recheck every measurement. |
These percentages are general planning examples rather than fixed rules. Large, high-value or structural pours should be reviewed by the project estimator, site manager and supplier before an order is confirmed.
A construction project often contains more than one concrete element. A warehouse floor, for example, may include the main slab, thickened perimeter edges, internal bases, loading-bay ramps and external paths.
One depth reading may underestimate an uneven excavation. Divide the area into a simple measurement grid and record the depth at several points.
Divide an irregular plan into smaller rectangles, triangles or circular sections. This is usually more reliable than applying one average length and width to the whole area.
Bagged concrete can be practical for small jobs and restricted-access locations. Ready-mix is commonly used for larger, continuous or time-sensitive pours. The lowest material price does not always produce the lowest complete project cost.
| Factor | Bagged concrete | Ready-mix concrete |
|---|---|---|
| Typical use | Small, staged or restricted-access work | Medium, large or continuous pours |
| Preparation | Mixed with water on site | Delivered ready for placement |
| Labour | More lifting, handling and mixing | Less manual mixing on site |
| Placing speed | Usually slower | Usually faster |
| Consistency | Depends on batching and water control | Produced under batching-plant controls |
| Access | Bags can be carried into confined areas | Requires truck, chute, conveyor or pump access |
| Purchasing unit | Complete bags | Cubic metres or cubic yards |
| Possible extra costs | Mixer hire, labour, water and handling | Delivery, small-load, waiting-time and pump charges |
| Unused material | Dry unopened bags may be stored correctly | Excess wet concrete needs an immediate plan |
The number of bags depends on the adjusted project volume and the finished yield of the selected product.
Bags required = Adjusted concrete volume ÷ Finished yield per bagAlways round the answer up to a complete bag. A result of 47.2 bags means that at least 48 complete bags are required.
A useful cost estimate separates concrete material from delivery, labour and equipment. This helps construction companies and developers compare supplier or contractor quotations more clearly.
Estimated material cost = Purchase quantity × Unit priceAn adjusted order contains 15.5 m³ of concrete. The entered price is 120 per cubic metre.
15.5 × 120 = 1,860Delivery, pump hire, workers, equipment, testing and tax would be added separately where applicable.
Contractors comparing a material cost with a proposed selling price can use the Margin Calculator to calculate gross profit, markup and profit margin.
A construction company needs to pour a floor measuring 12 metres long, 8 metres wide and 150 millimetres thick.
| Net volume | 14.4 m³ |
|---|---|
| Allowance | 7.5% |
| Adjusted volume | 15.48 m³ |
| Possible purchase quantity | 15.5 m³, subject to supplier confirmation |
A patio measures 20 feet long, 12 feet wide and 4 inches thick.
Depending on supplier increments and actual site conditions, the contractor may consider an order of approximately 3.5 yd³.
Each post hole has a diameter of 300 mm and a depth of 750 mm.
When the posts occupy a substantial part of each hole, deduct their embedded volume before applying the allowance.
Divide the driveway into two rectangular sections and calculate each one separately.
| Section | Dimensions | Thickness | Volume |
|---|---|---|---|
| Main area | 10 m × 5 m | 0.15 m | 7.5 m³ |
| Side area | 4 m × 3 m | 0.15 m | 1.8 m³ |
| Combined net volume | 9.3 m³ | ||
With a 7.5% allowance, the working requirement is approximately 10 m³ before checking the supplier’s ordering conditions.
For a driveway, road or parking project where asphalt is also being considered, compare material quantity using the Asphalt Calculator .
Use the result for preliminary material take-offs, supplier comparisons, procurement checks, variation estimates and planned pour quantities.
Compare early foundation, floor, parking, road, boundary wall and external-work quantities during project budgeting and contractor review.
Separate project elements, check contractor quantities and compare the calculated volume with drawings, schedules and bills of quantities.
Compare ordered quantities with actual pour progress and investigate unexpected increases or shortages during concrete placement.
Check the approximate number of bags required before mixing starts, especially for repairs, small pads, steps and post installations.
Use clearly recorded dimensions and allowances as a starting point when discussing order quantities, load sizes and delivery arrangements with customers.
Measure the length, width and depth of the space. Convert all measurements into compatible units and multiply them together. Apply a suitable allowance before deciding how much concrete to purchase.
Multiply the slab length by its width and thickness. A slab measuring 10 m × 5 m × 0.15 m has a net concrete volume of 7.5 m³.
Divide the adjusted project volume by the finished yield of one bag. Round the answer up to the next complete bag and check the stated yield for the product being purchased.
An allowance can be applied to the net concrete volume. The original volume, added percentage and adjusted purchase quantity should remain visible as separate figures.
The amount depends on measurement accuracy, excavation quality, formwork and the placement method. Carefully formed work may need a smaller allowance, while irregular excavation may require a larger one.
Divide the area into smaller rectangles, triangles or circular sections. Calculate each section separately, add the results, subtract large voids and then apply the selected allowance.
Multiply π by the hole radius squared and the hole depth. Multiply that result by the number of holes. The embedded volume of a large post may be deducted where it materially reduces the requirement.
Bagged concrete is often practical for small or restricted-access work. Ready-mix is normally more practical for larger continuous pours. Compare material cost, labour, equipment, access and required placing speed.
Yes, when the calculator converts them correctly. For a manual calculation, convert millimetres to metres first. For example, 150 mm equals 0.15 m.
Yes. Convert inches into feet before calculating cubic feet. Divide the cubic-foot result by 27 when a cubic-yard result is required.
Cement is a binding ingredient used to make concrete. Concrete normally contains cement, water, sand and stone aggregate in proportions determined by the required mix.
Reinforcement is not normally deducted from a routine concrete order because its volume is usually small compared with normal site variation. Follow the project measurement method where a formal quantity calculation is required.
No. It estimates volume, bags and material cost. Concrete strength, reinforcement, exposure class and structural dimensions must come from the project design and specification.
It can support preliminary estimates, procurement checks and site planning. Final commercial quantities should be checked against approved drawings, project documents and current site measurements.
Purchase quantities are normally rounded up. Bags must be bought as complete units, while ready-mix suppliers may accept orders only in set increments.
Use the calculated result as an initial material estimate, then recheck the dimensions, project specification, access arrangements, placing method and supplier requirements. Keeping the exact volume separate from the adjusted purchase quantity makes the estimate easier to review and can help prevent a costly shortage or unnecessary surplus during the pour.